Skip to content Skip to left sidebar Skip to footer

Update to Blower Door Requirement

Events, Training Opportunities and ConferencesArchive
EmPower+Archive
Residential Energy AssessmentsArchive
Comfort Home PilotArchive
Green Jobs – Green New York Residential FinancingArchive
General AnnouncementsArchive

To: Participating Comfort Home Contractors
Regarding Programs: Comfort Home Pilot Program
Summary: Update to Blower Door Requirement
Contact: [email protected]

All Load Reduction Installs with an On-Site Installation Date AND Assessment Date of 6/15/23 or later will REQUIRE both a Blower Door Test In and Out to be completed. If the Assessment Date is before 6/15/23 and the On-Site Installation Date is on or after 6/15/23 we will only require the Blower Door Test Out to be completed.

Scenario 1: Assessment Date: before 6/15/23 |Install Date: on or after 6/15/23

  • Pre Blower Door Test – optional
  • Post Blower Door Test – required

Scenario 2: Assessment Date: on or after 6/15/23 |Install Date: on or after 6/15/23

  • Pre Blower Door Test – required
  • Post Blower Door Test – required