NYSERDA will be Reinstating the 120-day Project Completion Goal
To: Participating AHP and EmPower Contractors
Regarding Programs: EmPower New York & Assisted Home Performance with ENERGY STAR®
Summary: NYSERDA will be reinstating the 120-day project completion goal
Contact: [email protected] or Questions can also be address with your account manager
In March of 2020, in response to COVID-19 and the statewide work pause, NYSERDA suspended Program project deadlines. Following the return to work, contractors still faced scheduling conflicts and supply chain issues, so NYSERDA kept the completion deadline suspension in place. NYSERDA is looking to gradually reinstate project completion deadlines to ensure projects are closed out in a timely manner. Related to this, CLEAResult has been reaching out contractors to have them prioritize their work in progress projects and close out any old projects that won’t be moving forward.
Starting January 1, 2023, the Program will reinstate the 120-day project completion goal. Please review the following dates for Project completion submission:
- Projects started before January 1, 2022, will need to be completed by January 1, 2023.
- Projects started before January 1, 2023, will need to be completed by May 1, 2023.
- Projects started after January 1, 2023, should be completed within the standard 120-day period.
We understand that there may be instances where a project cannot be completed within the timeframes referenced above. Contractors should document in the project notes in Uplight if a project can’t be completed within the timeframe.
For any questions, please reach out to your account manager or [email protected].